Operation & Maintenance

With drought conditions (or water emergency) upon us again Optimal Stormwater encourage sustainability and operations managers to contact our fully resourced stormwater harvesting team developed specifically to operate and manage public and private water utilities.

We are currently operating over 100 sustainable water projects including stormwater and rainwater harvesting, groundwater supply, leachate treatment and reuses and wastewater treatment and reuse.

We understand the value of water, where and how to source it and the most economic design for application and demand. Optimal were invited to draft the ACT Standards for Stormwater Harvesting and Reuse – the first of its kind which has been tested on the $20million ACT Stormwater Management Amplification program. Here are just a few of the project we are currently involved in.

City of Ryde Council – Investigate and Rectification Lardelli Stormwater Pond

In September 2019 Optimal Stormwater won the contract to undertake Investigate and Rectification Lardelli Stormwater Pond. The waterbody has both a water quality and water quantity function. In large events upstream lines overflow into the pond and it provides regional […]

view project details

2019 Randwick Council Operation & Maintenance

Optimal Stormwater have secured the OM Contract with Randwick Council to operate …(no ) of sustainable water schemes for the next … years.  Stormwater, rainwater  and wastewater (leachate) are treated and used to reduce potable water demand allowing Council to […]

view project details

Blackmore Oval Wetland and Stormwater Harvesting Project

After an arduous design journey Inner West Council sought contractors to deliver a hybrid design which repurposed an old RMS detention basin into an ornamental wetland and restore native flora and fauna to the site.  Stormwater was to be harvested […]

view project details

May 2019 City of Ryde Stormwater Harvesting Audit Rectification

Optimal Stormwater were engaged to audit Meadowbank Park and Ryde Park Stormwater Harvesting Projects.  The schemes are designed to supply treated stormwater for irrigation.  The Ryde Park Stormwater Harvesting Scheme collects flows from a 20ha catchment and includes Top Ryde […]

view project details

City of Sydney – 20 x Stormwater Harvesting Projects Audit, Rectification Optimisation & Operation

Following engagement for the Operation and Maintenance of 20 x stormwater harvesting plants for the City of Sydney, Optimal Stormwater provided a Infrastructure Operating Plan to bring all of these 20 plants to operational status. The overall operational status was […]

view project details

North Sydney Council – Stormwater & Rainwater Harvesting Upgrade Scheme (6 x Parks)

Optimal Stormwater was engaged to provide the North Sydney Stormwater and Rainwater Harvesting Upgrade Audit Report which included an audit, water quality and water quantity investigations, recommendations, energy efficiency analysis, water balance model and expansion options, project optimisation and upgrade […]

view project details

Mosman Council – Stormwater Harvesting Audit, Optimisation and Operation and Maintenance

Optimal Stormwater was engaged in late 2015 to provide the audit, optimisation and operation and maintenance the at Botanic Road stormwater harvesting scheme. The scheme was suffering from very high PH a consequence of using recycled concrete as backfill for […]

view project details

Hornsby Shire Council Epping Oval Stormwater Harvesting Design, Construction & Commissioning

Optimal Stormwater was engaged to provide $1.2M worth of stormwater harvesting works in Hornsby. Optimal Stormwater was selected because of our depth of understanding in regards to the water balance and limitations with the concept put forward. The design increased […]

view project details

City Of Sydney – Waterloo Oval, Stormwater Harvesting Construction & Commissioning

The project involved a drop offtake from the City of Sydney’s 600mm stormwater drain, with gravity feed into a CDS unit with a pumpwell next to the CDS. Flow tests determined that this arrangement would produce the most reliable supply […]

view project details

City of Sydney – Alexandria Oval, Stormwater Harvesting Construction & Commissioning

Optimal Stormwater was selected for the construction of a stormwater harvesting solution in Alexandria at Alexandria Oval for the City of Sydney. The project involved a drop offtake from a Sydney Water covered stormwater culvert, with gravity feed into an […]

view project details

Ku-Ring-Gai Council Cliff Oval, Stormwater Harvesting Design, Construction & Commissioning

Staff from Optimal Stormwater undertook the detailed design for the Cliff Oval Stormwater Harvesting Scheme in Wahroonga and assisted in the construction works with Austexc to install the solution. The project aims to irrigate two ovals from water harvested from […]

view project details

Sutherland Shire Council Cronulla Park, Stormwater Harvesting Design, Construction & Commissioning

The design of a stormwater harvesting reuse scheme at Cronulla Park included primary, secondary and tertiary treatment to achieve the desired outcome of irrigation without access control in a busy park as well as toilet flushing. The surface runoff from […]

view project details

Ku-Ring-Gai Council Allan Small Oval, Killara Stormwater Harvesting Design, Construction & Commissioning

Optimal Stormwater was selected for the Design and Construction of a large stormwater harvesting tank at Alan Small’s Oval in Killara. The project proved very challenging with once again hitting poor ground conditions, rock and water pouring through the site. […]

view project details

Shellharbour City Council Myimbarr Wetlands, Stormwater Harvesting Design, Construction & Commissioning

Optimal Stormwater was firstly engaged to do a peer review of another consultant’s design when costs blew out. As a consequence of the recommendations, Optimal was engaged to do a redesign of the project. The solution was innovative and involved […]

view project details

Kogarah Council- Council Depot, Stormwater Harvesting Design, Construction & Commissioning

Optimal Stormwater won the design and construction of a reasonably small harvesting system for the Kogarah Council depot at Carlton. A previous harvesting system was in place on a Sydney Water channel nearby, and Optimal Stormwater was selected to upgrade […]

view project details

Randwick Council- Clovelly Beach Stormwater Harvesting Offtake & Pump Station Construction & Commissioning

This project involved the construction of a new pumpwell, new offtake, new pump, new stormwater harvesting connections and new CDS rectifications. Clovelly Beach is now receiving recycled water from the scheme. The CDS unit now has a new reinforced lid, […]

view project details